Sl No | Service | Received | Approved | Rejected | Sakala.(Days) | Avg.(Days) | Median (Days) | Max.(Days) | Min.(Days) |
1
| Approval of Drawings [HT,DG&MSB] | 2 | 1 | 1 | Field Office(20 Days) | 20 | 20 | 33 | 7 |
2
| Approval of Drawings [HT,DG&MSB] | 2 | 2 | 0 | Head Office(25 Days) | 8 | 8 | 9 | 6 |
3
| Approval of Drawings [HT&DG] | 7 | 5 | 2 | Field Office(20 Days) | 8 | 7 | 20 | 1 |
4
| Approval of Drawings [HT&DG] | 6 | 6 | 0 | Head Office(25 Days) | 5 | 4 | 7 | 2 |
5
| Approval of Drawings [HT&MSB] | 31 | 23 | 8 | Field Office(20 Days) | 16 | 14 | 37 | 1 |
6
| Approval of Drawings [HT&MSB] | 14 | 11 | 3 | Head Office(25 Days) | 23 | 20 | 54 | 1 |
7
| Approval of Drawings [HT] | 53 | 27 | 26 | Field Office(20 Days) | 20 | 16 | 222 | 1 |
8
| Approval of Drawings [HT] | 8 | 5 | 3 | Head Office(25 Days) | 11 | 6 | 28 | 1 |
9
| Approval of Drawings [DG&MSB] | 1 | 1 | 0 | Field Office(20 Days) | 2 | 2 | 2 | 2 |
10
| Approval of Drawings [DG&MSB] | 1 | 1 | 0 | Head Office(25 Days) | 1 | 1 | 1 | 1 |
11
| Approval of Drawings [DG] | 39 | 23 | 16 | Field Office(20 Days) | 17 | 14 | 82 | 1 |
12
| Approval of Drawings [DG] | 11 | 10 | 1 | Head Office(25 Days) | 12 | 7 | 53 | 1 |
13
| Approval of Drawings [MSB] | 22 | 15 | 7 | Field Office(20 Days) | 10 | 10 | 22 | 1 |
14
| Approval of Drawings [MSB] | 1 | 1 | 0 | Head Office(25 Days) | 13 | 13 | 13 | 13 |
15
| | 7 | 6 | 1 | Field Office(20 Days) | 11 | 4 | 43 | 1 |
16
| | 3 | 2 | 1 | Head Office(25 Days) | 14 | 15 | 25 | 1 |
17
| BESCOM Approval of Drawings [HT] | 10 | 10 | 0 | -- | 75 | 6 | 687 | 1 |
18
| Installation Approval [HT,DG&MSB] | 3 | 2 | 1 | Field Office(20 Days) | 16 | 15 | 26 | 7 |
19
| Installation Approval [HT,DG&MSB] | 1 | 1 | 0 | Head Office(30 Days) | 43 | 43 | 43 | 43 |
20
| Installation Approval [HT&DG] | 10 | 9 | 1 | Field Office(20 Days) | 26 | 11 | 132 | 1 |
21
| Installation Approval [HT&DG] | 2 | 2 | 0 | Head Office(30 Days) | 32 | 32 | 49 | 14 |
22
| Installation Approval [HT&MSB] | 44 | 42 | 2 | Field Office(20 Days) | 37 | 26 | 261 | 1 |
23
| Installation Approval [HT&MSB] | 8 | 7 | 1 | Head Office(30 Days) | 28 | 22 | 62 | 1 |
24
| Installation Approval [HT] | 68 | 47 | 21 | Field Office(20 Days) | 38 | 28 | 240 | 1 |
25
| Installation Approval [HT] | 6 | 6 | 0 | Head Office(30 Days) | 20 | 14 | 43 | 1 |
26
| Installation Approval [DG&MSB] | 1 | 1 | 0 | Field Office(20 Days) | 9 | 9 | 9 | 9 |
27
| Installation Approval [DG] | 49 | 42 | 7 | Field Office(20 Days) | 29 | 22 | 110 | 1 |
28
| Installation Approval [DG] | 7 | 7 | 0 | Head Office(30 Days) | 16 | 16 | 34 | 2 |
29
| Installation Approval [MSB] | 17 | 17 | 0 | Field Office(20 Days) | 15 | 9 | 72 | 1 |
30
| Installation Approval [MSB] | 1 | 1 | 0 | Head Office(30 Days) | 1 | 1 | 1 | 1 |
31
| | 3 | 3 | 0 | Field Office(20 Days) | 12 | 13 | 22 | 1 |
32
| BESCOM Installation Approval [HT&MSB] | 3 | 3 | 0 | -- | 15 | 15 | 20 | 9 |
33
| BESCOM Installation Approval [HT] | 12 | 12 | 0 | -- | 9 | 8 | 23 | 1 |