New Updates


Name of the Service Selected Self Certification Form
Service provided by DEPARTMENT OF ELECTRICAL INSPECTORATE
View/Download Form 1        View/Download Form 2
Service Process
 ProcedureProcess
1 - The owner of any Electrical Installation up to 650V shall certify his Electrical Installation himself or by taking assistance of Licensed Electrical Contractor having valid license in the following formats, whichever is applicable for the particular installation.
2 - Form-I for voltage up to and including 250V
3 - Form-II for the voltage exceeding 250V and up to& including 650V
4 - The owner of the installation shall submit the report of the self certification to the concerned jurisdictional Electrical Inspector.
5 - Based on Self-Certification given by the owner, the power supply for commencement or recommencement after shut down for six months and above will be given by the supplier.

STATICTICS OF THE ELECTRICAL INSTALLATIONS (UPTO 650V AND EXCEEDING 650V):

  1. Total number of Installations for which power Supply was given by ESCOMS during year 2016-2017 : 8,54,964
  2. Number of Installations for which inspection was not required by this department and Supply was given (i.e. upto 650V) during year 2016-2017 : 8,11,875
  3. Number of Installations for which Approvals were accorded by this Department during year 2016-17 : 43,089

Based on Self-Certification given by the owner, the power supply for commencement or recommencement after shut down for six months and above will be given by the supplier